Road works are set to cause queues at the Elephant and Castle roundabout between February 29 and March 13.
All major resurfacing works spread over the two weeks will take place between the hours of 9pm and 5am, and are part of Transport for London’s ongoing £25m for the roundabout.
The first to be affected will begin with New Kent Road northbound and Newington Causeway on Monday Feb 29 and March 1.
Between Wednesday, March 2 and 3 the Elephant and Castle Link Road will be closed southbound, so road users are advised to use St George’s Road or Garden Road. Link Road northbound will be reduced to one lane on Saturday March 5 and Monday March 7.
There will be no access to the junction from Link Road northbound on Sunday, March 6, so use St George’s Road instead.
St George’s Road will be closed on March 8, and on the following day New Kent Road will be closed eastbound.
London Road will be closed southbound and Newington Causeway will be closed northbound on March 12. The final disruption will be the closure of Walworth Road on Sunday, March 13.